No coexistence period, no national transposition. If your investment project straddles this date, its legal framework changes midway.
One date, and one date only
Regulation (EU) 2023/1230 will replace Machinery Directive 2006/42/EC on 20 January 2027.

Three features make it a topic to address now rather than in January 2027.
- It is a regulation, not a directive: it applies directly, without national transposition, and identically throughout the Union.
- There is no coexistence period. From 20 January 2027, only the regulation applies to machinery placed on the market.
- Machinery placed on the market before that date remains governed by Directive 2006/42/EC. Existing equipment is therefore not affected by any retroactive switchover.
This last point is the most reassuring, and the one most often misunderstood. The regulation does not make your existing machines non-compliant overnight.
Read the rest of the guide
Enter your business contact details: you get immediate access to the whole of this guide and all INVOLTEC guides, on this device.
Coming up in the rest of the guide:
- What does not change
- What changes: digital technology comes within scope
- The real issue for a manufacturer: assembling a line
- What this changes for your investment planning
- Used machines and retrofits: two cases to distinguish
- The most common mistakes
- … and 2 more sections
What does not change
Let’s start here, because this shapes how the rest should be read.
The general logic of CE marking remains: the manufacturer assesses the risks, applies the essential health and safety requirements, compiles a technical file, draws up a declaration of conformity and affixes the marking.
The concepts of assembly of machinery and partly completed machinery remain, each with its own rules: partly completed machinery is accompanied by a declaration of incorporation rather than a declaration of conformity, and does not bear the CE marking.
A company familiar with the Directive is therefore not discovering an unknown system. It is discovering a system that is more demanding in three areas.
What changes: digital technology comes within scope
The regulation’s first contribution is to explicitly include what the 2006 directive had not anticipated: embedded software, updates, self-learning functions and connectivity.
In practical terms, the risk assessment must now cover:
- risks linked to embedded software and changes in its behaviour over time;
- risks introduced by updates, including those carried out remotely;
- cybersecurity aspects affecting safety functions;
- risks linked to connecting the machine to other equipment or to a network.
For a modern packaging machine — PLC, HMI (human–machine interface), data reporting to an MES, remote maintenance — this is not theoretical. A machine whose PLC accepts remote updates is a machine whose safety depends on controlling that channel.
The second contribution concerns documentation, which may be supplied in digital form, with associated availability and retention obligations.
The third concerns the highest-risk machinery, for which third-party involvement is strengthened.
The real issue for a manufacturer: assembling a line
This is the point buyers identify least often, and the one with the most practical consequences.

Buying a CE-marked machine and operating it on its own raises no particular issue.
Connecting several pieces of equipment — cartoner, overwrapping machine, marking, conveying, case packer — so that they operate together to achieve the same result is another matter. You then create an assembly, and that assembly must in turn undergo its own risk assessment and conformity process.
The question to settle at the start of the project is therefore simple to state and often difficult to get settled: who is responsible for the conformity of the assembly?
There are three possible configurations:
- an integrator takes on the assembly and assumes responsibility for its conformity;
- the user company assembles the equipment itself and becomes responsible for the assembly;
- each piece of equipment remains independent, with no functional safety link — a configuration that is rarer than people think as soon as stops are interlinked between machines.
This point must be set out in black and white in the specification and in the contract. Discovering it at acceptance is the most costly situation.
What this changes for your investment planning
The reference date is the date on which the machine is placed on the market, not the order date.
A project signed in 2026 for delivery in 2027 therefore straddles two regimes. Three questions should be put to the manufacturer at the tender stage:
- under which regime will the machine be placed on the market, given the planned delivery schedule?
- what happens if delivery slips beyond 20 January 2027?
- will the documentation supplied comply with the regime applicable on the actual date of placing on the market?
There is nothing contentious about these questions. They simply prevent a schedule slip, which is common on this type of project, from turning into a compliance issue.
Used machines and retrofits: two cases to distinguish
A used machine placed on the market before 20 January 2027 remains governed by the regime under which it was placed on the market. Reselling a used machine within the Union does not in itself constitute a new placing on the market.
However, a substantial modification to an existing machine may lead to it being regarded as a new machine, with the corresponding obligations for whoever carried out the modification.
The line between maintenance, improvement and substantial modification is not always clear. It is assessed case by case, depending on whether new risks arise or existing risks are increased.
This is a point to investigate before launching an upgrade project, not afterwards. Practical guide no. 16 covers the choice between retrofit and replacement.
The most common mistakes
Believing that existing machines become non-compliant. Machinery placed on the market before 20 January 2027 remains governed by Directive 2006/42/EC. There is no retroactive switchover.
Basing your reasoning on the order date. It is the date of placing on the market that counts. A schedule slip can change the applicable regime.
Failing to decide who is responsible for the assembly. As soon as several machines operate together, someone must be responsible for the conformity of the assembly. If the contract does not say who, it is generally the user company.
Treating cybersecurity as an IT issue. Once it affects safety functions, it falls within the machine’s risk assessment.
Launching a retrofit without assessing the modification. A substantial modification can give rise to manufacturer’s obligations for whoever carried it out.
10 questions to ask before signing in 2026
- Under which regime will the machine be placed on the market, given the delivery schedule?
- What happens if delivery slips beyond 20 January 2027?
- Will the machine be delivered as complete machinery or as partly completed machinery?
- Who is responsible for the conformity of the assembly formed by the complete line?
- Is this answer included in the specification and in the contract?
- What functional safety links exist between the items of equipment on the line?
- How will software updates be carried out, recorded and validated?
- Can the machine be accessed remotely, and under what rules?
- In what form will the technical documentation be supplied, and for how long?
- Have the maintenance and HSE departments been involved in reviewing the specification?
Conclusion
Regulation (EU) 2023/1230 does not overturn the logic of CE marking. It extends it to digital technology, strengthens documentation requirements and tightens the treatment of the highest-risk machinery.
For a manufacturer running packaging lines, the practical issues come down to two points: the actual date on which equipment ordered in 2026 is placed on the market, and responsibility for the assembly when several machines are connected.
Both points are settled in the specification, on a single page. They are not settled at acceptance.
Sources
Regulation (EU) 2023/1230 of the European Parliament and of the Council of 14 June 2023 on machinery and repealing Directive 2006/42/EC.
Entry into force: 19 July 2023. Application: 20 January 2027, with no coexistence period.